|

Latest News
AccuRATE V1.1.3.0
The latest version of 2nd Gen BTP
Assessment tools has been released.
DoP agree to a new Pilot to
commence early February 2007.
BASIX (DIY)
Review
ABSA instrumental in securing DoP
DIY Sustainability Tool - DoP Review...not independent but a starting point
Visit the ABSA Site for further
details.
DIY found to lower the standard of
Residential Building BTP in NSW - varies between 200% to 400% below Simulation
Method when compared with NatHERS and far more variation expected to AccuRATE.
| |
ESD materials
Embodied Energy
Inherent in the wastage of almost any
material is associated energy that was used in its making: energy used in
extraction of raw material from the environment energy used for transportation
energy used during manufacture energy used again for transportation energy used
in its placement in the building and energy used in demolition.
In order to amortise the energy used it would be prudent to recycle or reuse the
material to avoid at least some of the energy used in extraction manufacture use
and in the waste streaming.
The subject of embodied energy requires
adequate space for explanation and is a topic worth publication in its own
right. As a guide the following tables haves been included here for reference
and as a guide only:
Embodied Energy (Process Energy
Requirement or PER)
| Organics |
MJ/kg |
Ceramics |
MJ/kg |
Metals |
MJ/kg |
| Kiln dried sawn
softwood |
3.4 |
Stabilised Earth |
0.7 |
Mild Steel |
34.0 |
| Kiln dried sawn
hardwood |
2.0 |
Imported dimension
granite |
13.9 |
Galvanised Mild Steel |
38.0 |
| Air dried sawn
hardwood |
0.5 |
Local dimension
granite |
5.9 |
Aluminium |
170.0 |
| Hardboard |
24.2 |
Clay bricks |
2.5 |
Copper |
100.0 |
| Particleboard |
8.0 |
Cement |
5.6 |
Zinc |
51.0 |
| Medium density
fibreboard |
11.3 |
Gypsum plaster |
2.9 |
|
|
| Plywood |
10.4 |
Plasterboard |
4.4 |
|
|
| Glue-laminated timber |
11.0 |
Fibre cement |
7.6 |
|
|
| Laminated veneer
lumber |
11.0 |
Insitu concrete |
1.9 |
|
|
| Plastics general |
90.0 |
Precast steam-cured
concrete |
2.0 |
|
|
| PVC |
80.0 |
Precast tilt-up
concrete |
1.9 |
|
|
| Synthetic rubber |
110.0 |
Concrete blocks |
1.5 |
|
|
| Acrylic paint |
61.5 |
Autoclaved aerated
concrete |
3.6 |
|
|
|
|
Glass |
12.7 |
|
|
Embodied Energy (Process Energy
Requirement or PER)
Walls
Timber frame timber weatherboard plasterboard lined wall
Timber frame reconstituted timber weatherboard plasterboard lined wall
Timber frame aluminium weatherboard plasterboard lined wall
Timber frame clay brick veneer plasterboard lined wall
Steel frame clay brick veneer plasterboard lined wall
Double clay brick plasterboard lined wall
Cement stabilised rammed earth wall
|
MJ/kg
188
377
403
561
604
472
376
|
Floors
Elevated timber floor (lowest level)
Elevated timber floor (upper level)
110 mm concrete slab on ground
110 mm elevated concrete slab (permanent formwork)
200 mm precast concrete T beam/infill flooring
|
MJ/kg
293
147
645
665
644
|
Roofs
Timber frame timber shingle roof plasterboard ceiling
Timber frame concrete tile roof plasterboard ceiling
Timber frame terracotta roof plasterboard ceiling
Timber frame steel sheet roof plasterboard ceiling
Steel frame steel sheet roof plasterboard
|
MJ/kg
151
251
271
330
483
|
The concept of an environmentally damage free material
presupposes that:-
- no extractive processes are required to secure the base materials
- the material is renewable
- the material is applied to building construction with low energy demands
- the completed building system has good comfort and aesthetic performance
- at the end of the building's life the material can be returned to the
environment without residual damage, or can be recycled to be used again in
another new building development.
Existing SystemsWorking
within existing available
building systems, materials choices may be made where very few of the above
attributes are secured directly, or other pragmatic priorities possibly with
environmental consequences might be added to the list.
This practice uses a substantial amount of steel in some
projects. Normally such a material derived from extractive
mining, with high energy inputs to form the material and further form useable
products from the material and its fabrication requirements would be judged
environment unfriendly.
However the driving priorities favouring steel in a pro-environment
context included:-
-
|
| that the building could be substantially pre-fabricated and erected
on-site initially with only hand tools, |
|
| erected on-site from within the final building 'footprint' with minimal
damage to the surrounding site |
|
| erected with minimal support machinery until the renewable energy system
is operating on the building which then powers the support machinery rather a
generator
|
|
| that pest invasion and attack is
minimised as a consequence of use
|
Such materials are readily available, well understood
by industry and regulatory authorities; and approvals are achievable; although
advocacy is needed for these less usual applications of materials made by this
practice (notably the use of light industrial steel sections for residential
structures).
Assumed to be 'environmental'The practice also
has been involved with the use of materials usually
associated with favourable environmental performance: recycled timbers, stone
salvaged from on-site, stabilised rammed earth using site excavated material to
bench the building, mud brick and aerated autoclave concrete.
Some regulatory authorities have little experience with some of these, and it
is not unusual for advocacy to be needed on individual concerns raised by such
regulators. These concerns include: the structural capacity of recycled or
handmade materials, waterproofing of surfaces and materials, guarantees as to
definition of colour of surfaces of material embodying natural materials in the
completed building.
None of these concerns has a real basis in; it is
more usually only the unfamiliarity with the material and its applications by the
outside observer which causes concerns or objections.
Fully renewable materialAn example of an emergent ecological material
is straw bale construction. There are few local examples of this
construction; expertise, prior examples, draft building codes and so on are all
sourced from overseas. As a result local building industry and authorities
are perplexed by proposals embodying these materials. Approvals are obtainable
by energetic advocacy including the ESD merits and the local application of
precedent, technology and experience from elsewhere.
Why devote effort to such building construction?
This building system embodies most of the desirable ecological material
priority characteristics:-
-
|
| the material is sourced from waste in the normal agricultural process,
being the remnant stalk usually burnt or turned into the soil |
|
| new material is generated in the farm
rural cycle each year |
|
| the material is biological, with no extraction processes needed |
|
| the material achieves R6 insulation characteristics |
|
| at the end of the building life, the material is returned to the
environment by mulching
technology, existing buildings, and draft building codes information is
centred in the US. |
The most commonly asked questions about straw bale construction material
relate to :-
- structural safety
- fire
- vermin
- moisture
- None of the purported characteristics
of any of the building material claimed are found in the reality.
- The complete building system includes
straw in a pressed
and bound bale with fire retardant applied as for cellulose insulation,
(boric acid) and an external fire resistant render skin.
The building system as a whole does not support combustion.
- Vermin find the hollow cellulose structure of the straw bale
unpalatable due to the low cellulose density and regular air
pocket in the matrix of the material. Vermin is also excluded by damp proof
course and render envelope which are part of the building system.
- The rendered envelope and damp proof membranes built in as for
other masonry systems means that the system is not subject to water
ingress or logging.
Similar to other masonry systems, the material can be erected as infill to
a framed building, or as load bearing masonry. In either system the
material is internally reinforced with pins between bale layers, and externally
reinforced with mesh in the render envelope.
There is substantial local experience with 'Dri-bond' walls where loose
stacked hollow concrete blocks form the core and a glass reinforced render
envelope provides structural rigidity. In load bearing construction for
straw bale, the external reinforcing and render fulfils the same role;
additionally full height tie rods and a wall plate bond beam is integral to
the straw bale system of construction as for autoclave concrete walls.
Thus all of the characteristics of straw bale construction are as found in
other conventional masonry systems.
There is some settlement in wall
height during construction of load bearing straw walls, and the tie down and
bond beam design allows for this.
There is nothing alien or technically difficult in the building system.
Successful application depends on design understanding the system
features, and construction practice allowing for these issues.
Traditional construction systems, notably kiln fired masonry situated on
reactive soil sites, have a long history of problems in use; including
substantial cracking prejudicing structural integrity, but this hasn't stopped
their use.
|